Qatargas marks major milestone for NFB Living Quarters Expansion Project
«قطر غاز» تنجز مشروع توسعة «السكن البحرية لحقل الشمال»
Doha: Qatargas Operating Company Limited (Qatargas) achieved a major milestone with its North Field Bravo (NFB) Living Quarters Expansion (LQX) Project as it safely and successfully completed the onshore fabrication of the living quarters structure by Nakilat-Keppel Offshore Marine (N-KOM) at the Erhama Bin Jaber Al Jalahma Shipyard.
The project is significant for Qatar as it is for the first time that a major offshore living quarters structure has been entirely fabricated at a local yard in the country. This aligns with Qatargas’ commitment to Tawteen, the supply chain localisation programme initiated by Qatar Petroleum for the energy sector. A key element of this commitment is supporting the realisation of the Qatar National Vison 2030 in supporting local companies engaged in knowledge and technology-based businesses.
Qatargas organised a ceremony to mark the sail-away of the jacket and topside of the structure at Ras Laffan. The event was attended by Qatargas’ shareholders and senior executives, Nakilat- Keppel Offshore & Marine Ltd (N-KOM), and the project’s contractor, Rosetti Marino.
Speaking at the ceremony, Khalid bin Khalifa Al Thani, CEO, Qatargas, said: “This project is a historic milestone for the State of Qatar as it highlights a new and important capability. It is for the first time that the fabrication of a major offshore structure of this magnitude has been completed in a Qatari yard.
This achievement showcases the capabilities, skills and resources which are available locally at the Erhama Bin Jaber Al Jalahma Shipyard for the fabrication of large and complex offshore structures.”
He added: “I congratulate the project team, including the contractors, who successfully ensured its delivery and were able to overcome the challenges that are expected of projects of such a scale and nature. This is a positive reflection of the dedication and commitment demonstrated by all parties.”
Nakilat’s CEO Abdullah Fadhalah Al Sulaiti, said: “We are proud to be delivering this project in a safe, timely and efficient manner to support the growth of Qatar’s energy industry.
This project is not only a milestone achievement for Qatar but also an excellent testament to N-KOM’s experience in handling offshore fabrication projects.”
He added: “I would like to congratulate the entire project team for their dedication and commitment that has led to this milestone achievement and extend my appreciation to our long-term standing partner Qatargas for their strong support and trust throughout this period.
Moving ahead, we look forward to handling more large-scale projects that are made with pride in Qatar, for Qatar. This will further complement our existing range of maritime services being offered. We are confident of our ability to continue providing our customers with safe, reliable and efficient services.”
Qatargas previously awarded the Engineering Procurement & Construction (EPC) Contract for the LQX project to Rosetti Marino who undertook engineering designs for the project in Italy. All the fabrication work was undertaken by N-KOM at the Erhama Bin Jaber Al Jalahma Shipyard at Ras Laffan Port.
The project provides for additional living quarters which will increase the capacity of the NFB Offshore Living Quarters by 90 personnel on board. When fully installed, this will allow for the catering of additional operational requirements.
The project work scope includes the construction of a four-legged jacket and piles weighing approximately 2200 tonnes.
This will support the new living accommodation platform weighing approximately 2800 tonnes and consisting of five decks, a fully equipped helideck, six bridge links to existing living quarters, services and utilities.
The project has recently achieved 2.5 million safe man-hours without any lost time incidents with a peak manpower rate of over 900 persons.
The next major milestone of the project is the safe transportation and installation of the 5000 tonnes of structure to offshore NFB in February 2020. The load out, sail away and installation activities will be carried out by subcontractor Heerema using their heavy lift vessel ‘Aegir’.
The original NFB accommodation, installed in 1995, was designed for the operational needs of Qatargas Trains 1 and 2. The offshore accommodation expansion project was initiated to cater for the changes in the operational requirements following various expansion projects. Brownfield modifications will also be done on the existing living quarters and platform to properly integrate the new additional living quarters.
استطاعت شركة «قطر غاز» للتشغيل المحدودة (قطر غاز) تسطير إنجاز بارز في مشروعها الخاص بتوسعة منصة السكن البحرية لحقل الشمال «برافو»؛ حيث نجحت في إكمال تصنيع الهيكل الفولاذي لمنصة السكن البحرية بأمان، وذلك من خلال شركة «ناقلات كيبل» للأعمال البحرية المحدودة في حوض «ارحمة بن جابر الجلاهمة» لبناء وإصلاح السفن.
ويحظى هذا المشروع بأهمية خاصة بالنسبة لدولة قطر؛ حيث إنه ولأول مرّة يتم تصنيع هيكل فولاذي رئيسي لمنصة سكن بحرية بشكل كامل في حوض محلي في الدولة. ويأتي هذا المشروع تماشياً مع التزام «قطر غاز» ببرنامج توطين الخدمات والصناعات في قطاع الطاقة «توطين»، وهو مشروع أطلقته «قطر للبترول» بهدف تعزيز توطين سلسلة التوريد في القطاع، بما يعزّز تحقيق رؤية قطر الوطنية 2030، من خلال دعم الشركات العاملة في المشاريع القائمة على المعرفة والتقنية.
حفل
وفي سياق متصل، قامت «قطر غاز» بتنظيم حفل بمناسبة شحن وتحميل دعامات الهيكل الفولاذي وجزئه العلوي من «راس لفان»، وقد حضر هذا الحفل ممثلون عن مساهمي «قطر غاز» وكبار المسؤولين التنفيذيين في الشركة، وشركة «ناقلات كيبل» للأعمال البحرية المحدودة، ومقاول المشروع شركة «روزيتي مارينو».
وقد ألقى الشيخ خالد بن خليفة آل ثاني، الرئيس التنفيذي لـ «قطر غاز»، كلمة في الحفل قال فيها: «إن هذا المشروع يعدّ إنجازاً يشهد له تاريخ دولة قطر؛ حيث إن هذه هي المرة الأولى التي يتم فيها إكمال تصنيع هيكل فولاذي بحري رئيسي كبير بهذا الحجم في حوض قطري. وهذا الإنجاز إن دلّ على شيء، فإنما يدلّ على القدرات والمهارات والموارد المتوفرة على الصعيد المحلي في حوض (ارحمة بن جابر الجلاهمة) لبناء وإصلاح السفن لتصنيع الهياكل الفولاذية البحرية الكبيرة والمتطورة».
اعتزاز
وفي معرض تعليقه على هذه المناسبة؛ صرّح المهندس عبدالله فضالة السليطي، الرئيس التنفيذي لشركة «ناقلات»، قائلاً: «إننا نشعر بالفخر والاعتزاز لتنفيذ هذا المشروع بصورة آمنة وبكفاءة عالية، وفقاً للجدول الزمني المحدّد، وذلك من أجل دعم نهضة صناعة الطاقة في دولة قطر. وإن هذا المشروع ليس إنجازاً بارزاً لدولة قطر فحسب، بل هو أيضاً خير دليل على الخبرات العريقة التي تتمتّع بها شركة ناقلات كيبل للأعمال البحرية المحدودة في تنفيذ مشاريع تصنيع منصات ومنشآت بحرية».
وفي السياق نفسه، منحت «قطر غاز» -في وقت سابق- عقد الهندسة والتوريدات والإنشاء لمشروع توسعة المساكن البحرية إلى شركة «روزيتي مارينو»، والتي نفّذت التصاميم الهندسية للمشروع في إيطاليا. وقد تم الاضطلاع بتنفيذ أعمال التصنيع كافة من قِبل شركة «ناقلات كيبل» للأعمال البحرية المحدودة في حوض «ارحمة بن جابر الجلاهمة» لبناء وإصلاح السفن في ميناء راس لفان.
ويُذكر أن هذا المشروع سيوفّر مساكن إضافية من شأنها أن تزيد من عدد نزلاء المساكن البحرية، بواقع 90 شخصاً. وسيعمل هذا المشروع -عند اكتمال تركيب جميع الوحدات السكنية- على تلبية الاحتياجات التشغيلية الإضافية.
ومن الجدير بالذكر أن ما يزيد على 900 شخص عملوا في هذا المشروع قد أتمّوا مؤخراً 2.5 مليون ساعة عمل بشكل آمن دون وقوع أي حادث مُقعد عن العمل.